Montfort Drive Reconstruction

  • Project TypeBond / CO Project; Capital Project; Streets / Sidewalks
  • Project StatusEngineering Design Phase

Part of Proposition B of the 2019 Bond Program is reconstructing Montfort Drive from Belt Line Road south to the city limit line north of Paladium Drive. Montfort Drive was originally built in the early 1980s. There will be some minor utility work as a part of this project. Some of the Master Transportation elements will be installed as a part of this project.


Status Updates

April 2024

City Council approved Change Order # 1 to the design contract, expanding the limits 500 linear feet south of the current project limits through the Paladium intersection and reducing the vehicle lane geometry to increase pedestrian and landscape opportunities on Montfort Drive. 


March 2024

The Town has received the 60% plans from the design engineer for review. 


December 2023

The town has received the 30% conceptual plans from the design engineer for review. It is anticipated that the 60% plans will be completed at the beginning of March 2024.


April 2023

City Council awarded a Professional Services Agreement for the design of Montfort Drive Reconstruction to Kimley-Horn and Associates.